A short history of where and when I worked...based very loosely on Studs Terkel's great work on a book of the same name...
Sunday, September 30, 2007
More Changes
The framing crew and I came together pretty well and we were able to exceed our production quotas easily. The younger Hawai’ian members of the crew would disappear around
Then we started hearing rumors. True; men on construction sites love to gossip! And the gossip was all about the mistakes being made by the other framing crews and then whole wings of completed drywall being removed because backing strips were absent or in the wrong place. Big layoff’s! We were still the ‘good guy’s’. None of our work had been faulted, but once a contractor gets into the ‘firing’ mode, it is hard to tell the good guy’s from the bad guy’s. And every one is suspect.
It was about this time that
I seem to remember that we were already framing on the 21st floor with 3 more to go. So, framing wasn’t a problem area and I was assigned to a drywall crew. Some good things had been said about me and this was going to be my foremen’s ‘test’. I decided to press the issue and said, “No, thanks.” And told them I wanted foreman’s pay now and not at some later date if they wanted me to run a crew. That worked, I got the pay and I was told not to tell anyone else.
I returned to the 11th floor and began re-installing drywall. We quickly moved up the tower and were soon installing on the 14th floor.
Success? It was not be. All of the foremen were asked to attend a meeting at
Well, I didn’t have to agonize over a decision. Should I quit? Ha! The next morning found me at the Carpenter’s Union hall and talking to my new friend, the business agent. He informed me that
Thursday, September 20, 2007
Back to Work
Meanwhile, back at the
As I was saying earlier, I was supposed to be the foreman of the layout crew, but as it worked out, Frenchie didn’t want to go home to
And as I also said, I was the only non-Hawai’ian on the crew. Haole. The crew spoke what I learned was called ‘pidgin’. An interesting blend of English, Polynesian and maybe some Tagalog from the
I also learned something about the Hawai’ian work ethic; which was minimal. Half of our crew would disappear around the time for our first break of the day and we wouldn’t see them again till the next morning. As the foreman in pay only, I wasn’t too concerned. It was Frenchie’s problem and he never seemed to notice their absence.
A little something about Frenchie; he was originally from
Even with just half a crew present and accounted for, we used lots of shortcuts and were soon cutting our allotted layout labor budget in half. Frenchie’s response to this was to slow down. He really didn’t want to get back to
I was soon frustrated and began to talk to the powers above and asked to be given something with more responsibility. This was soon given to me. I had a framing crew now and a goal of framing all of the walls on a floor within a week. I also had a crew of Hawaiians. OK, the work began…
Wednesday, September 19, 2007
I Recall
A thought or two that I had yesterday while I was mowing the orchard. I was thinking about the fact that my career suited my personality. I have always enjoyed working alone and that was something I could do in the construction business. Early on, when I was an apprentice and working ‘piece work’ on houses and apartments, I always worked alone because that was how you made the most money. And you quickly learned that having someone nearby who might strike up a conversation would cost you money in the long run. And when you did have to work with someone, the best partner was one that knew what to do without being told.
I can remember many days of working on high rise buildings, installing the panels that made up the skin of those building, and never saying more than a dozen words. You controlled the crane with hand signals and the crew knew what they were doing without being told; if they didn’t… you didn’t want them around. It was far too dangerous.
Working as a foreman or superintendent meant that you didn’t spend a lot of time in conversation. You have very few friends when you’re the boss. And I remember making lots of people upset because I wouldn’t let them work with a partner. I knew that production would increase when people worked alone and I was always right. Part of my job was to make sure that conversations didn’t occur during the workday.
What a grouch!
Monday, September 17, 2007
Driving
Now that I had a job, I had to get used to a long commute. 75 miles, one way. I started the job in the spring of 1977 and so the trip was quite pleasant; certainly better than half that distance on a
I would have to get up early; maybe
When I started the job, the steel frame of the hotel tower was complete up to about the 16th floor, with 11 more floors to go. Concrete had been poured to about the 12th floor. We (Oahu Interiors) had begun framing and had completed the framing from the 3rd floor to the 7th. And my job, laying out the walls, had progressed to the 10th floor.
Drywall installation hadn’t started yet as we were waiting for the exterior panels to be installed and that was still a few weeks off. And that also meant that we had a great and unobstructed view of the Truckee Meadows from our vantage point on the 10th floor.
One of the things we could see from that floor was a huge open pit gravel mine. It had to have been over 300’ deep and was located about a quarter mile from the new hotel tower. And because this pit was so deep, it had to be dewatered 24 hours a day by huge pumps that returned the water to the
(At the completion of the hotel project, the pumps were shut off and the pit became a lake, still to be seen in the parking lot.)
Sunday, September 16, 2007
And away we go...
I'm going to leave out the high drama of our moving saga and move directly into the world of working...
After moving to
I went to the Carpenters Union and talked to the Business agent. I had been given his name and a letter of recommendation from the Union that I had left in
A little something about Oahu Interiors. Sometime in the 60’s, a drywaller,
Since
Monday, September 03, 2007
Continuing the trip…
Sure enough, 30 minutes later I drove into Susanville on a beautiful fall afternoon. The temperature was in the low 70’s and I learned later that the next morning would bring a ‘below freezing’ mark. There were fall colors everywhere, making the little town quite spectacular; at least for this city boy!
I found a motel to stay in, in the downtown area. As I remember it, there were no more than 4 or 5 motels in town, and this one was clean enough. Then I drove around the city, which didn’t take long. After dinner I decided to walk and see the town close up. It was certainly quiet; there was no comparing it to
The next day I walked around town again, stopping once for breakfast and then looking in the windows of the various real estate offices I passed. According to the ads I saw, the prices of land and houses were fantastically low. Ranch acreage ran from $100 to $500 an acre and houses were down in the $25,000 range.
I finally found a real estate office that was open and went in. Mike Egan Realty and
Long story, short… I found the house we would move to in the little
What does this story have to do with Working? Hang on, more to come...